| Notice ID: | 63192 |
| Notice Type: | Planned Service Outage |
| Critical: | Y |
| Notice Status Description: | Initiate |
| Reqrd Rsp Desc: | No Response Required |
| Posting Date/Time: | Apr 23 2026 1:20 PM |
| Subject: | MAY 2026 --- FGT ZONES 2 AND 3 MAINTENANCE - 1ST UPDATE |
| Notice Effective Date/Time: | May 11 2026 9:00 AM |
| Notice End Date/Time: | May 16 2026 9:00 AM |
| Notice Text: |
FGT will perform maintenance at FGT Compressor Station 8. The start date has been modified. This maintenance will now start May 11, 2026, and is to be completed by the end of gas day May 15, 2026. During this maintenance FGT may continue to schedule up to 1,000,000 MMBtu/day through Station 8. During normal operations, FGT schedules up to 1,075,000 MMBtu/day through Station 8. FGT maintenance previously scheduled for May 2026 has been completed. FGT will schedule up to the normal capacity of 1,250,000 MMBtu/day through Station 9. |